Tata Power Solar has achieved another milestone by commissioning 95MW(DC) in Dhuravan, Gujarat. The area stretch for the project is 324 acres. The project has a robot cleaning system.
The project is a foundation of strong relations between Tata Power Solar and Gujarat State Electricity Corporation Limited. It displays the trust GESCL has displayed in Tata Power Solar. Along with this, the installation exceeds on all the safety and quality parameters stated by the government.
About 3.0 Lakhs domestic modules were used in the project giving an impetus to domestic manufacturing. Around 25 inverters of 3MW each were used. 13 Inverter Transformer out of which 12 were used for 6.3MVA; 1 was used for 3.15MVA. Approximately 650KM of DC cable were laid, the plant was commissioned before schedule even after facing delay of a few days due to monsoon. Plant was commissioned and operational acceptance was achieved in the 1st attempt.
The project encountered few distinctive challenges such as a delay of 54 days during the construction phase due to monsoon (heavy rains). The whole site was submerged in water up to 1mtrs of height. The soil type was slushy; hence the movement of machinery became difficult.
Being a pioneer in the solar industry, Tata Power Solar's EPC expertise empowered us to create customized structural support for a smooth execution at the project site.
Apart from this, for this entirely automated plant, we introduced RF-based SCADA system which helped in wireless communication between the machines. Tata Power Solar takes pride to showcase this landmark project.
Tata Power Solar has touched another milestone by commissioning 300MW DC in 2GW Pavagada Solar Park, Karnataka for SoftBank Group. The installation area stretch was 270 acres. The commissioned project has an installation of robot cleaning system. The entire area has grading at 2 degrees for Robo movement, motion sensors in street light and heavy canopy with motorized gate. Along with this, the project matches all the safety and quality standard parameters as per government mandate.
Approximately 9,05,138 modules were used in the project which includes Crystalline, Risen etc. to name a few. For the smooth processing of the installation, 16 Inverters (rating 3.125 MW), 4 Inverter Transformers (rating- 12.5 MVA), and 2 Power Transformers (rating- 25 MVA) have been used.
The project faced few unique challenges like delivery of major equipment, limited timelines, short supply of cables etc. Despite many hurdles, our highly experienced project execution team backed by deep understanding of the technology, helped deliver the project before time. Various technologies like Boom pressure for Roof slab, Mobile app for RFID-Module & drone survey for topographical understanding was used in the process of commissioning.
Pavagada Solar Park has provided us a unique opportunity to enhance our generation with 2GW capacity of the installation. Establishment of solar project in this area is seen as a one of the pioneers in Solar Park in the entire Country.
Location: Mumbai, India
Tata Power Solar commissioned 820.8 kWp at Cricket Club of India (CCI), Mumbai in 100 days.
The Stadium was inaugurated by Shri Devendra Fadnavis, Honourable Chief Minister of Maharashtra.
Tata Power Solar joined hands with Cricket Club of India to utilise the potential of solar energy. The installation of this solar rooftop project helped to generate over 1.12 million electricity per year, which led to 25% of savings in the power consumption cost.
At present, on an average (apart from Stadium Flood lights, which run on DG), the Stadium consumes 4 lakhs kWh /month. However, with the new solar installation, on an average basis the consumption from the grid would fall to approximately 3 lakhs kWh/month.
CCI will also be able to curb the emission of over 840 tonnes of carbon dioxide annually.
Mr. Premal Udani, President, CCI and Mr. Rakesh Kapoor, Vice Chairman of Infrastructure and Green Technology Committee, CCI said, “We continuously look at projects which promote renewable energy focus, and are glad to partner with Tata Power Solar to execute this landmark project for us. They have delivered on the promise of the brand TATA. We have set an example to use rooftop space in the stadiums to help protect the environment.”
Mr. Ashish Khanna, President, MD & CEO, Tata Power Solar said, “After executing the world’s largest Rooftop in a single location and India’s largest carport at Cochin International Airport, Tata Power Solar has installed the world’s largest Rooftop in a Cricket Stadium at CCI Mumbai, in a record period of 100 days.”
Tata Power Solar has entered into a Power Purchase Agreement (PPA) with GE to provide solar rooftop solutions for six manufacturing and services sites in India.
Tata Power Solar will install solar rooftop projects at manufacturing sites located at Durgapur in West Bengal, Pallavaram and Hosur in Tamil Nadu, multi-modal manufacturing site at Pune and upcoming factory at Marhowra in Bihar and maintenance facility at Roza in Uttar Pradesh.
The project will be executed on Build-Own-Operate basis.
Mr. Amit Kumar, Vice President, Supply Chain - GE India & South-East Asia said, “India is an important manufacturing base for GE and sustainability is at the core of our business. Generation of solar power at our manufacturing plants will help us in reducing our carbon footprint. The country has a lot of potential for solar rooftop projects which need to be harnessed to meet India’s energy needs for manufacturing.”
Ashish Khanna, President, MD & CEO, Tata Power Solar said, “The project underlines our leadership in project commissioning space and reflects GE’s commitment towards enhancing solar energy for its manufacturing units. It also demonstrates GE’s confidence in Tata Power capabilities in providing reliable solar power through competency in rooftop solutions. We are hopeful that the renewable segment will also be encouraged by these cost optimized energy solutions.”
Supporting Tata Steel’s initiative in reducing carbon footprint, Tata Power Solar commissioned a 3 MW Solar PV Power Plant in the Iron Ore Mine at Noamundi. This is the 1st Solar Power Plant of its kind solar power plant at any iron ore mine in the country. The project will help in reducing CO2 emission by about 3000 tonnes per annum.
Reiterating Tata Steel`s commitment to clean energy, Mr. Narendran said: "We have constantly looked at opportunities to exploit renewable energy sources. This is yet another milestone in our quest to become a sustainability driven company, committed to exploring clean energy solutions. Renewable energy is the best way of mitigating the impact of climate change."
Synergy between three Tata companies, namely, Tata Steel, Tata Power Solar and Tata Power Trading Company was instrumental in shaping the project into reality. With Tata Steel as the sole buyer of all electricity at a contracted tariff, this partnership demonstrates Tata Steel's commitment to climate action and voice support for supporting a strong outcome at the UN Climate Change Conference Paris 2015 (COP 21).
Mr. Khanna said: "We are very glad to execute this project as it represents a huge step towards bringing the sun’s clean, sustainable energy as a part of a hybrid system which has grid power as well as fossil fuel as an option. This project epitomizes new technologies for a sustainable and continuous power requirements and such plants demonstrate how energy needs of the manufacturing sector can be met through clean and renewable sources like solar and has the potential to take usage of solar energy to a new heights."
Solar modules convert the solar radiation into electricity which is converted through inverters to AC power at suitable voltage and then fed to the utility grid with net metering facility for accounting of the solar electricity. In case of complete outage of grid, the solar plant has the capability to synchronize with existing DG bus at processing plant Noamundi and continue operation.
The plant covers 19 acres of land at an elevated reclaimed mining hill with ample undulations and a very rocky terrain. Solar lights have been used for boundary and area lighting around the solar plant. The selected site has a potential of 4.5 MW solar power generation.
A rain water harvesting system has been set-up to collect all surface run-off from rains and module cleaning activities to serve as make-up water and minimize module cleaning water requirement. Horticulture has been planned under the solar panels that will add to the aesthetic value and will reduce cleaning water requirement by binding the loose top soil.
The Agency for Non-Conventional Energy and Rural Technology (ANERT) along with the Government of India and Kerala initiated a program to harness the power of the sun to light up rural & sub-urban areas of Kerala.
The government was responsible for short-listing and empaneling key vendors, to install, commission and maintain the solar systems. Tata Power Solar, based on its credentials and proven ability, was selected and empaneled as one of vendor for the project.
With many vendors being registered with ANERT, the people had a choice, for purchasing their solar power systems. People overwhelmingly gave an order of 7700+ systems, to Tata Power Solar, being the largest order for a single vendor, based on their Trust in the Tata brand & the quality of systems and services provided by the company.
Savings for Families & the Kerala Government: The power generated through solar system suffice the energy needs of the families, hence less dependency & stress on the DISCOM, in turn helping the state reduce its load on the distribution system. (Considering 300 sunny days in a year)
Employment Generation: The installations have generated employment for the locals. The project also generated employment opportunities for the local people, who trained themselves for installation and equipment servicing.
Powering for the Generations: Most of the beneficiaries of this project are senior people, whose families may be settled outside the village or country. The solar system helps them enjoy a basic lifestyle with amenities like lights, fan and television at their disposal, along with access to communication devices, which help them stay connected with their families across the world.
The 17MW Mithapur power plant, located in Gujarat and completed in 2012 is proof of our ability to provide quality power solutions that are innovative in design and are timely executed, thus providing value for all stakeholders.
In an effort to fulfill its Renewable Purchase Obligation (RPO) a 17 MW solar power plant in Mithapur, Gujarat was built.
The project was completed in a time period of 9 months and commissioned in January 2012.
In its two years of operation, the project is performing at 83.80% performance ratio and generating more than 30 Million kWh of electricity per year.
The Mulshi power plant, a 3 MW solar power plant designed and constructed by Tata Power Solar in March 2011, provides energy to over 2 million homes and has led to employment for the local community.
Tata Power Solar commissioned a 3 MW solar power plant for Tata Power in March 2011 using the cells and modules manufactured in-house.
The project was built on 13 acres of land with the natural landscape of the site preserved.
This solar PV plant in India at Mulshi was completed in a record time of nine months and made operational in two phases – 1 MW and 2 MW, commissioned in January and March 2011 respectively.
Dell Inc. is an American multinational computer technology company that develops computers and related products and services. Dell is pairing technology with innovation to make a positive social and environmental impact – building a Legacy of Good. They were looking to invest in clean green energy in their Indian facilities, and partnered with Tata Power Solar to integrate solar power in their energy mix.
Dell is green conscious company, trying to generate green power wherever possible, thereby reducing the load on the environment. At their facility in Bengaluru, they already have a rooftop solar power plant installed.
Dell had two objectives when they were looking at green energy, namely – power the office premises with renewable energy and reduce the usage of energy for cooling the building during summers.
Tata Power Solar offered to commission a vertical solar system, which would produce the essential clean and green energy to power their office and also cut-off direct sunlight from hitting the building, thus keeping it cool during summers.
This is the 1st time in India that a vertical solar installation has happened on an existing building.
27 years and counting: the Tata Power Solar journey at a glance, a history rich with experience and achievements.
Here are all the latest happenings from the world of Tata Power Solar